Sharing Target and Roadmap dates between plan and program

crystal.escalante@greensky.com
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 4, 2023

Context: We have a routine each week where we manually sync target dates from our respective Plans, into "roadmap target dates" in a combined / enterprise Program view. Is there a way to simply automate the carryover of the "Target Dates" to "roadmap start/end dates"?

1 comment

Comment

Log in or Sign up to comment
Jean-Emmanuel BANQUEY
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
May 9, 2023

Hello,

Why not using the same fields in Plans and other usual Jira views ?
I personally use "target start" and "target end" on plans and I added them on the regular issue view so it's clear for everyone and always in sync