I'm using the improved planning interface with portfolio 3.15.
I noticed that a release on the timeline is marked as 'off track' when all its issues are in the Closed/Done state. I suppose this is because the end date of those issues is after the end date of the release. The issue-dates are automatically set based on the sprint dates. (However, I notice the same behavior when I manually set the end date to somewhere after the release date) And when I manually set the dates to anytime before the release's end-date it shows as 'on-track'
I would expect that releases will be marked as 'off-track' only when un-closed issues are scheduled to end after the release's date. Is this behavior as designed, did I overlook a setting or just discovered a bug?
Question - are the tickets that are marked Closed/Done also marked with a resolution?
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.