We have been using Portfolio for about six weeks and JIRA for years. In our workflow we have a "ready for release" state that is the equivalent of resolved/closed in that we supply the value to the resolution field. I've update all the transitions to this state to use the resolve issue screen and am firing a resolve issue hook on transition. However, no matter what I do, the % complete on JIRA Portfolio only seems to update if I close the issue. I thought that this status was based on the resolution field. Am I missing something?
Solved! Go to Solution.
(facepalm) YES! That was it. This status has to be in the done category on the status edit screen. Thanks so much Darren.
Haha, no problem at all buddy :)
Strange that the color is the trigger -- according to the Portfolio progress tracking page (https://confluence.atlassian.com/jiraportfolioserver/status-and-progress-tracking-715263088.html#Statusandprogresstracking-Resolved), the resolved field just has to be not empty.. "If the issue is resolved ( Resolution field is not empty), the progress is 100%." when there are no sub-issues.