In portfolio for Jira server 12.2 version, I have the following setup:
- a plan which refers to an agile board which gathers issues by a filter
- from 7 different jira projects
- restricted to Epic-Link is not EMPTY
- so in the filter I have around 1400 issues (showing correctly on the agile board)
BUT
in my portfolio plan the scope view seems to be limited to 477 issues on the story-Level ?!
That means also that I have Epics without issues assigned from which I know this isn't true, it's only because of the missing issues in portfolio. In the plan I do have all filters cleared and I am far away from the issue limit of 5000, so I do not understand where the issues get lost.
Any idea?