Hi there,
I am checking out Jira portfolio these day and wonder, whether it is possible in the "improved UI", to schedule the availability time and times off for team members as it was in the classic UI.
Thanks a lot!
Hi
I don't believe it is - see this page here - see:
Managing capacity
Previously, you'd be able to plan the individual capacity of your team members.
In the improved interface, individual capacity planning is replaced by team capacity planning. When auto-scheduling a plan, the total capacity of a team to complete the work being scheduled will be taken into account. To do this, you must directly set team capacity in your plan.
You can also see details in this page - see:
Shared people settings – Since individual capacity planning is not supported, any configured settings for global availability and absences and team availability and exceptions will not apply to plans with the improved interface.
It appears there are suggestions for this - for example, vote/follow this one: JPOSERVER-2616
Ste
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.