A question for Jira Portfolio use:
How does Portfolio calculates team capacity for future capacity? Our team sprint capacity is 348 hours per sprint (2 week). Portfolio looks like this for future sprints. Why isn't the sprint (2) full instead it calculates work also for sprints 3 to 6? We don't have any dependencies in our stories. Shouldn't almost all capacity be on the sprint 2?