Hi,
I've been using Jira Advanced Roadmaps for a month or two now, but mainly for organizing a view across projects into initiatives and epics, and hypothetical scheduling. I'm using the new interface.
I'd like to now use the auto-schedule feature to see what proposed timelines will look like. I'm running in to a problem, namely that auto-schedule is always resetting the duration for any ticket to 1 day. I've tried setting
It's not clear to me from the documentation which values the auto-schedule uses in its algorithm, and which ones it will respect as given.
Any tips are welcome.
Thanks!
Hi Earl,
thanks for the detailed response. I'll set aside time this week to try and experiment with the project settings to see if I can figure out what's causing this 1-day estimation. I'll report back once I have some findings.