I am wondering if there is a way I can add some ''lead'' time in a JIRA task that can be reflected in PLAN.
Exemple:
- Task: pouring concrete takes 2 days
- lead time: concrete needs to cool down 5 days before the next task can start (walls)
How can I address this issue? Estimating 7 days of work would be innacurate.
Thank you for your help,
David
Solved! Go to Solution.
Hi Dave,
I am not using auto-schedule so adding a zero estimate issue could do the trick. I was trying to avoid adding a new task for lead time but it seems to be the only option so far.
Thank you for answering so fast to my question!
David
No worries, happy to have been able to help!