One of the teams I am working with has a stable velocity, but will be having a specialist join the team for a few Sprints to address some specific (related) work.
The team want to show increased capacity/velocity in Portfolio to reflect the work they are doing, but they also need to velocity to drop back down after the specialist leaves the team to ensure they don't take on too much work for later releases.
In short:
What is the best way to achieve this in Portfolio?
Solved! Go to Solution.
Thanks very much Kevin!
When I read you answer I first thought it sounded a bit like a hack, but having tried it I've found it's a really clean solution.
Minor problem: The Capacity Report now shows the temporary team as over capacity by >1000% and the team they are helping as completely free. Both teams are assigned to the same Sprint as per the advice above. Is there any way to fix this? I've tried un-allocating the teams and re-allocating, but still see the same result.
Many thanks!