I am using portfolio with a kanban team. The team contains 9 members with 40 hrs per week capacity. I have 6 stories. 5 of them are assigned to 5 members of the team (one per person). Portfolio therefore predicts each story will take a month to perform based on one assignee doing a story. The capacity shows that for each week, I have 4 member of free capacity left. My 6th story is not assigned to anyone. This 6th story is assigned to a different release but this release as the same start date as the other release to which the other 5 stories are tagged.
In the portfolio setting, I have set the option that up to 12 people can work on a single story. Therefore, I would expect that this 6th story that is unassigned would use up the capacity available each week and start in parallel with the 5 others. Instead, portfolio forces it to start only once the other 5 assigned stories are done. When I look at the capacity, it is ridiculous because I see that my team is occupied at 50% during the time the team works on the 5 assigned task. HOw can I force parallelization of the tasks.
thanks
Mathieu
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.