Hi,
I am new to JIRA portfolio. We are looking to use this for Release tracking.
I really don't know if it can calculate the Fix release date based on the estimates provided against the Issue.?
If we want to check the plan vs actual progress does it have the ability to do so?
I saw that it has baseline start date, Baseline finish date, but I observed that it does not shift those dates based on the estimate against the issue, and same goes with other available dates ,i.e start date and end date. Does this mean that we have to manually add dates against each issue? or am I missing something here.
Thanks
Deepak
Hello Deepak,
The Releases can be configured as a Fixed release or a dynamic release, the Dynamic Release will calculate the release dates where the Fixed dates are set manually. This is covered here in more detail.
Tracking the Progress and status of the issues in the plan is covered in this Documentation
As for Baseline start dates which are you referring, Portfolio has Earliest Start, Target Start, & Scheduled Start.
Regards,
Earl
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.