Hello,
I made a plan with two filters. In dependancy View i had dépendancies between two Epics. I need to know wich tickets implements those Epics.
So my question is how to configure the dependancy view in order to show all tickets in every Epic concerned by the dependancy ?
Thanks
@Rym I'm not quite sure where to start. I'll assume for now you are referring to the Gantt view. Can you provide a screenshot of your current plan and the view you are working with? It could be as simple as having the badge setting for dependencies vs. line setting.
If it is the dependencies report PERT chart then make sure you don't have it rolling up to any level or have any filters.