I have 2 tasks with a Finish to Start dependencies. How to I get the start date of Task B to be automatically pushed out when Task A end date is pushed out?
Solved! Go to Solution.
@Michael AndolfattoI've checked our settings. All set to sequential. Currently we are planning on Initative level only (without epics/stories/sprints). Initative A+B+C all linked with a "blocks" dependency. Initially all of them were auto-planned. All fine. Then I've moved Initiative A to a later start date, overlapping Initative B. Automated Planning of B+C (without A) won't change anything. B ist overlapping A. Appreciate any help, hint, comment. Regards and thanks in advance.
Hi @Raimund Antonitsch , the auto-scheduler in Advanced Roadmaps will only move issues that have estimates applied (either time or story points) which is very rarely the case for high-level issues like Initiatives.
Advanced Roadmaps really excels from the bottom-up: the start date/end date of an issue like an Initiative is dependent on the scheduling of the lowest-level (estimated) items.
I've been looking for an answer to the same question for a while now :D
I've never used the auto-scheduler before, this doesn't work with manually adjusting start/finish of a task by any chance, does it?
Hey @Anna Poppe ,
No, there is no functionality for this as far as I'm aware. The blocked task will only have its position adjusted by the auto-scheduler or manually by a user moving it directly.
I would definitely recommend playing around with the auto-scheduler- it can be really helpful to use it as a foundation of sorts for your plan's timeline which can then be adjusted manually afterwards.