How do we visually roll up story points to the initiative level (Our highest configured issuetype)? ie: We need to see rollup (accumulated) as they roll up from a Story to Epic and then up to Initiative level? We also would like to see roll up of hours from sub-task all the way up to Initiative. Maybe for the hours we add time tracking to Epics and Initiatives. But the story point rollup I am confused as how to configure this.
Any links to documentation would be very appreciated.
Thanks,
Steve Josue
Solved! Go to Solution.
Daniel,
This was some unexpected, awesome help. We build a rollup plan for Velocity and then another one for hours and they worked great!!
Thank you!!
-Steve Josue