In the advanced roadmap there are start and finish dates. I'm looking to add predecessors similar to that of MS project where a task has to finish before the next one starts. I can not seem to figure out how to do this - if one date moves all the downstream dates need to move to - all I see is to do it manually, is there a way around this
The roll up feature works within a task but it doesn't link from one task to another :( Is that the only way?
To clarify, you'll need to manually add the dependencies using the 'link issues' feature and then the roll-up feature will help make it so that if one task gets adjusted, it adjusts everything.
Hope that helps.
Jacob
enter in all tasks then use link issue and when one date moves out it updates downstream?
That's the idea, yup. It'll also move upstream meaning that your epic would update as well with a new adjusted end date potentially.
Jacob
Bonus tip, beyond the great advice provided by @Jacob Vu
Set your dependencies to be Sequential for your Plan. That way Advanced Roadmaps knows that is how you want to manage dependencies and will offer warnings and will auto-schedule with that in mind.