Given Jira projects:
where
- pA has an epic pA.e1 that has story pA.e1.s2
 - pB has an issue pB.i1 with a remaining estimate of 4w
 - pA.e1.s2 depends on pB.i1
 
and
- MyPlan's issue sources = pA
 
what advanced roadmaps setting and/or plan setting and/or view settings are needed to show that after 'Auto-schedule':
- pA.e1.s2 is adjusted to start after pB.i1 is resolved (now + remaining estimate)
 - pA.e1.s2 has a dependency on pB.i1
- I do see the incoming dependency badge
 - I'm hoping to see another more obvious indication like a new row the in the dependency management view showing a link between pA.e1.s2 and pB.i1
 
 
Thank you!!