We use 2-week sprints in our teams. Jira Advanced Roadmaps also does. But the start dates of our sprints differ from the dates in de view Sprint Capacity management. How can I change these sprint start date?
Solved! Go to Solution.
I hear you on this, but that is not what I see happening. The dates are a couple of days off of each other.
Hi @André Tiggelaven ,
Can I just confirm if you're using the older "Live Plans" interface or the newer improved interface (recently rebranded as Advanced Roadmaps). I'm also wondering if you're using Cloud or Server?
It's worth noting that the Live Plans interface has been deprecated so we're not going to be making any further changes to the interface. The newer interface (on the Roadmap tab) should show the correct sprint dates (either based on dates configured for future sprints or projected by iteration length from the active sprint).
Maybe you can add a screenshot to show the problem as it might help understand it better,
Regards,
Dave
We had an update of Jira Portfolio. After the update the sprint dates were corrected. I'm confident now,