Portfolio ignores priorities defined in the "scope" and generates an incomprehensible and completely irrelevant schedule. Is there a way to force it to schedule the work in the order I need it to be scheduled?
Solved! Go to Solution.
Thanks Thomas.
I am using Kanban, so sprint assignments are out of question. I don't have many dependencies, so this is also out of question.
There are some release assignments but it doesn't seem to affect it much. In fact, it prioritizes things I need for releases very low, making them unachievable.
So far my experience with JIRA Portfolio is 99.5% frustration and 0.5% hope that it might work out somehow.
Regards,
Sergey
Rank and release assignments are definitely what should drive your schedule for estimated issues.
It's not impossible for Portfolio to be impacted by custom JIRA configuration so I strongly encourage you to reach out to support here!
I'd be happy to help further if you have some screenshot to ensure we have a concrete example to solve but those usually fit better support cases for privacy reasons.
Cheers,
Thomas