Hi Community
Disappointed that the Advanced roadmap reporting can't display actual vs targeted on the Gantt chart, this is pivotal to drive conversations around Programmes of work in a portfolio with any stakeholders. If there is a way can someone help ?
Hey Amit, thanks for the response.
Not sure if we use Actual date in our environment, in essence when you have a roadmap of projects with target start and end dates, they inevitably creep due to issues, sometimes that creep can be significant..
In products like MS Project you can overlay both the Target Dates and Actuals to explain if an Issue (Project) is running to time or delayed and go into root cause analysis. At the moment you can only Gannt either of the dates