Can you track dependencies in advanced roadmaps other than blocks? We use all of the linked options and i would like to track that in my advanced roadmap.
Solved! Go to Solution.
Excellent. One last recommendation for you to consider -
You/your team needs to determine a defined business process to educate your users on what issue link type to use under what situation when working with plans. Otherwise, you will loose control of your plans' issues dependency due to too many different issue link types.
Please click on Accept Answer when you have a chance.
Best, Joseph