Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

BigGantt tasks near Critical Path

Justin Valdez
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 10, 2025

BigGantt does a great job of showing THE critical path, but is there a way or feature to show other tasks that are close to the critical path? 

1 answer

1 accepted

0 votes
Answer accepted
Sahir Maharaj
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 11, 2025

Hello @Justin Valdez

Based on my experience, BigGantt’s critical path feature highlights tasks that directly impact project timelines, but tasks close to the critical path may require additional configuration.

One option is to use custom views or filters to identify these tasks based on slack time or dependency types.

Creating a custom column to display the slack time might help visually identify tasks that are near-critical.

 

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events