Background:
"Advanced Roadmaps for Jira (ARJ)" is primarily offered as a tool to plan and track work across multiple teams / projects. It can 'pull' and 'show' data from different sources: Projects, Boards, and Filters. In most cases, ARJ deals with existing Backlog Items residing in different Projects. [source: Advanced Roadmaps Guide | Jira Software | Atlassian ]
Question:
Creating and Managing Themes and Features (higher level Backlog items) - Which is a better Practice ?
Option A: Identifying and Adding New Higher Level Backlog Items - [like Themes and Features] in the ARJ first - before they are created in individual Team's Jira projects. Each Team picks up one or more Features from ARJ and add more details in their Project level / Team level plans [like adding Jira Epics and Stories]
Option B: All Backlog items at all levels are first created in individual Projects and 'pull' them 'together' to create a Plan in ARJ.
Please share your thoughts.
Thank you so much for very helpful response!
Just to confirm my understanding.....:
Option A: Maintain ONE Jira Project [Master Project] for all teams; Create a Plan in Advanced Roadmaps for Jira (ARJ) based on just one Master Project with the desired Hierarchy levels. Always create new Issues [at any level] on Jira Master Project only; use ARJ for high level planning and Roadmapping, what-if scenarios, etc. This Option is VERY CLEAR.
Option B: Maintain Collaborative Issues in ARJ while keeping Team-specific Issues in individual Team's Jira Projects.
This brings up another question about representing work items in Jira / ARJ that need collaborating with other teams in general:
Scenario 1: Each Team plans and delivers their own items using Jira Projects. They don't have any dependencies; they can plan and deliver independently. The ARJ provides 'visibility' into the work all the Teams in a single place for Managers and others. If the work of these teams contribute to achievement of higher level items (like Features, Themes, Initiatives, etc.)
Scenario 2: Each Team has their own Backlog and the associated Project. Additionally, Each Team has a need to collaborate with 5 other Teams.
For example, Team A (a Platform Development Team) builds their Product [which is the Platform itself] that is used by other Teams to build their products. [Teams 1 - 5].
Sorry for the long message :)
Any help / guidance is greatly appreciated!!!