Hello,
we have set up the initiative level on top of the issue type hierarchy and testing the child epic/story/task warnings with target dates exceeding the parent end date, which works fine. However I can`t seem to find how to show a warning in another initiative that I`ve linked as a dependency:
example: IN-1 is linked to IN-2 with a "is blocked by" link type. IN-1 has a child epic EP-1 which has a child story ST-1 with an end date set later that EP-1, therefore I see a warning on IN-1, EP-1 and ST-1 but no warnings on IN-2. Is there a way to enable this?