Advanced Roadmap configuration - For Completed issues what is a higher limits

AsmitaD
September 16, 2020

. It works for 150 days i want to see the done issues for more that a year say 400/500 days. possible ?

1 comment

Comment

Log in or Sign up to comment
Jonny Adams
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
September 16, 2020

Hi @AsmitaD 

  1. Go to More > Completion date.
  2. Select which filtering time frame you'd like to use for completed issues.

Then,

  1. Go to More > Completion date and open Schedule range.
  2. Select the schedule's range you want to filter by.