The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

issue that estimated for today schedule for a day jira portfolio

Natalie Maharaban
March 5, 2019

Hello 

i have issues that estimated for 2 days and the scheduled in portfolio (start -end date )display the issue only as 1 day 

thanks! 

image_2019_03_04T06_56_25_833Z.pngimage_2019_03_04T07_05_26_737Z.pngimage_2019_03_04T12_05_32_060Z.pngimage_2019_03_05T06_52_21_617Z.png

1 comment

Comments for this post are closed

Community moderators have prevented the ability to post new comments.

Earl McCutcheon
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
March 6, 2019

Hi Natalie,

Go to the "plan configurations >> Scheduling >> Maximum assignees per story", the default value here is going to be 3, so even though you have 16 hours for an 8 hour work day up to 3 team members can be assigned to the issue to spread the load of that issue across the associated team members.

You can either reduce the "Maximum assignees per story" value to 1 so that there is only one assignee per story, and you should be all set.

Additional details on the steps for configuring this setting can be seen here:

Regards,
Earl

Natalie Maharaban
March 8, 2019

thank you ! 

Like Earl McCutcheon likes this
Earl McCutcheon
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
March 8, 2019

You're Welcome :) happy I could help