Im looking for a way to track how my orgs advanced plan has changed over time.
I'm running into this issue right now. I ran an Auto-schedule today and it broke a bunch of dates.
Hi @Ollie Reid,
Can you provide a bit more context on how it broke then dates.... in theory there are a couple of levels of protection for this. Firstly you have to actively accept the auto-scheduling suggestion and then you need to save the changes from your scenario back to the rest of Jira.
So in theory you could have either cancelled the auto-scheduling or discarded the changes? I'm guessing that in this instance you didn't notice until it was too late and you now want to compare with a previous version of the plan and restore the previous date values?
The changes made should be in the change history of each issue, but depending on the size of your plan that could be an arduous task to recover those dates.
So in this case is the goal not just to be able to compare with a previous version of the plan but actually to be able to import or restore the data?
Regards,
Dave