Hi, hoping someone can help with this query.
I have a team which is showing on JIRA Plans as having 118 story points assigned to the sprint. However when I view the sprint the team only has 80 points in the sprint.
Does anyone know how I can get the story points on the Plans view to be updated correctly?
thanks @Jean-Emmanuel BANQUEY - do you know how I can filter to see the "16 issues not assigned to sprint"?
Hi @Kevin.Bruce
Did you try to click on the first link jjust below "View backlog in Jira"
I think it should be ok with a specific focus on green statused issues.
Have your Jira project admin check the sprint board as it may have statuses like - descoped or duplicates etc. not being visible when you are looking at the sprint itself.
If you run an issue report for the team where sprint = {your specific sprint} then this might highlight as well where the missing 38 points are.