Hello,
In Advanced Roadmaps for scrum teams the Capacity is defaulted to 30 points, and I realize I can change that, but it for all sprint for that team.
I have a PI plan that is built out for 8 teams that consist of 3 - 2 week sprints for each team.
Since I know planned time out of the office for any given sprint I would like to be able to set a Capacity velocity per sprint.
So let's say for Team Green has a base level of 44 points per sprint.
In Sprint 1 - 2 people will be out for planned time off and In Sprint 2 - 3 people will be out for planned time off, but the Capacity can only be set for all sprints.
Is there I way we can set different values for each sprint?
Solved! Go to Solution.