Hello,
Is it possible to show the issues with missed due dates are marked in red colour in the advanced roadmap ?
Right now the road map just puts a yellow triangle to those items.
Kind Regards,
Manas
Hi Dave,
Thanks for sharing so many details. I am working on a roll-out where the business team and IT team are going to work together. The business team will not be using JIRA, but they will have access to the confluence where they will have a view of how things are going. As they are used to seeing traffic light signal reports, it is very easy if they can see things in red amber or green based on the risks we have.
So if we have missed a deadline and it is still open, then it is clearly red.
You have raised a few things which are important. I had not thought about due date vs target end date. Does Jira have a definition of these fields and how we should use them ?
Hi @manas Sahoo ,
Jira does have a field called "Due Date" which is used by default in Advanced Roadmaps for the end date. You can configure Advanced Roadmaps plans to use alternative fields for dates (see the "Scheduling" section of the plan config).
The limitation of this is that the standard Roadmaps tool will not render a timeline from alternative end dates.
But end date is just a field that you can use if you would like to - semantically it probably has more meaning than target end for the absolute deadline of when the work needs to be completed.
I'll take this feedback to our design team though for consideration about future colouring options!
Thanks,
Dave
hi @Dave ,
In this case, is there any feature / gadget which can help with the conditional formatting of timeline bars which can visually show that a particular EPIC is delayed in the timeline view if the due date is in the past or give a visual indication of delay.