On Portfolio version 3.1 - new experience.
I do not understand how the "Target start" and the "Target end" fields are computed by the scheduler.
My configuration is:
After auto-schedule, the start date and end date are as follow:
I would have expected that the minimum would be the estimates with potentially the weekend added.
I would also assume that, due to the dependency, the minimum elapsed days would be 40 days whatever the team capacity is as the documentation states that there is only one assignee by issue.
Solved! Go to Solution.
Dear Dave,
I have tried again and now it is working as expected, but:
* I had to "save the change in JIRA"
* I had to refresh the browser page
While it is ok for me, it could be annoying if you want to play with your planning without wanting to commit the changes back to JIRA.
Best regards,
Bruno
Hi Bruno,
It shouldn't actually be necessary to save the changes to Jira, however I do know that we had some issues with the estimates fields not triggering a refreshed calculated schedule (we cache old calculation results if we don't believe any data has changed) caused by a failure to recognise that the field value has changed.
This can occur when immediately clicking on the "Auto-schedule" button with focus still in the estimate field and should hopefully be resolved in 3.2.0.
If you continue to have problems with this then I would suggest that you raise a support issue as this sounds like a bug,
Regards,
Dave