We have started to convert to using JIRA portfolio's Capacity views to track higher-level cross-team capacity for multiple engineering teams. This works great 85% of the time and the other half of the time I get into this weird invalid point calculation state where it seems to default the point totals to the capacity for the team.
In the Sprint Board Backlog View - I will see 12 issues, adding up to 48 points.
In the Portfolio Capacity View for that sprint - I will see 12 issues (correct), adding up to 55 points (incorrect)
55 is the capacity set for the team so I am assuming if it can't calculate the total - it defaults to the capacity?