This is a Portfolio plugin question.
We use the Portfolio plugin to help implement SAFe. With SAFe you have a 2 to 3 day planning meeting once every 6 sprints. For that reason every 6th sprint you only plan half the team's velocity. Does anyone know how I could reduce the velocity of a sprint by x amount at the team level?
Thank you very much for the helpful tips. I will try out some combinations you recommended. I think I started by reducing work load for each team member during the sprint dates.