In the JIRA sprint backlog I can see all standard issues (149) for that sprint label, but when I create a plan timeline view for the same initiative and filter for the same sprint label it's only showing 40 issues.
Why have I "lost" over 100 issues? I would expect to see all issues in my plan that I've filtered for that sprint label.
Sprint backlog vs Timeline plan
Hi @Helen Platt
The default period "done" issues are shown in a plan is 30 days.
As I see on the screenshot of your sprint the sprint is like 10 weeks. Check the plan settings as mentioned by @Ste Wright