I have set up a plan in Jira Portfolio that has many initiatives (Kanban based)
One of the initiatives represents a year long initiative in my plan where I need Portfolio to "spread" the hours I have estimated for the initiative from the Target Start Date to the Target End Date.
I have allocated hours to this initiative, and a team is assigned to the Project that has this initiative. However, this initiative has a clear start and end date - it should NOT end prior to the Target End date.
Portfolio is currently ending the initiative "too soon" because it thinks it can get done earlier given the effort allocated and the capacity available.
How can I get Portfolio to actually "stretch" the initiative from Target Start to Target End.