The default working hours per day in our JIRA setup is 6h, in Advanced Roadmaps it is 8h. The problem that we are encountering is that Advanced Roadmaps is taking the estimated hours and converting them into days which screws up the estimates being shown in AR: An estimation of 5d (30h) in JIRA is being turned into 3.75d in AR. This makes planning difficult.
I am aware that it is possible to display the estimations in hours, but having numbers with three digits for an estimation like 196h, isn't helpful at all for various reasons.
Is there a way to change the default working hours per day in Advanced Roadmaps or inherit the settings from JIRA?
Thank you!
Mark
Solved! Go to Solution.
Hi @Ste Wright ,
Thanks for the quick response. I will raise a bug as suggested.
On a different note: It's a different topic but related to the improved interface and a potential issue I have noticed: Do you know if it is by design that the estimates of tasks/stories/etc are not being summed up in the epic in the improved interface? If not, I will raise another bug.
Cheers,
Mark
You can activate the roll-up of estimates:
Ste
@Ste Wright FYI: After I raised the bug I got feedback from a support engineer and unfortunately, it is not a bug :/
"With the new experience release, we have set the working hours to 8h per day and this is non-configurable. This is mentioned in the documentation below:
Changes in the improved interface
The following settings from live plans are also used as default:
- Working hours and days
- Region: System default
- Work day: 8 hours
- Work week: Monday through Friday
So it's not possible to customize these Working hours and days settings anymore in the improved interface."
Thanks for letting me know!
I've updated my original answer to include this information.
This might not be a bug, but if you think having this option configurable would be beneficial, you can still raise it as a feature request :)
Do that from this page: https://jira.atlassian.com/secure/Dashboard.jspa
Ste