BigGantt does a great job of showing THE critical path, but is there a way or feature to show other tasks that are close to the critical path? 

1 comment

Comment

Log in or Sign up to comment
Sahir Maharaj
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 11, 2025

Hello @Justin Valdez

Based on my experience, BigGantt’s critical path feature highlights tasks that directly impact project timelines, but tasks close to the critical path may require additional configuration.

One option is to use custom views or filters to identify these tasks based on slack time or dependency types.

Creating a custom column to display the slack time might help visually identify tasks that are near-critical.

 