We are applying SAFe framework for our planning and delivery model and need to inset a hardening sprint after every 3 sprints. Is there a way in Jira to create these sprints in advance and drop the team velocity for the hardening sprints? our goal is to stabilize code in the hardening sprint and no new user stories to work on...
as an example , when team estimated an Epic, its telling me we have 8 sprint of work to finish it based on story points. However that would mean 8 sprints back to back with no hardening sprint. If we do 1 sprint of hardening after every 3 sprints then the delivery of that epic, would not be exactly 8 sprints rather 8 sprints + 4 hardening sprints would be more like 12 sprints duration for delivery
has anyone been able to use hardening sprints in Jira and pre create these sprints...?
Thanks