I have a backlog and a to-do column and I want to move anything mistakenly put in to-do to backlog

JERRY SAULMAN August 17, 2023

I am hoping for a way to move a card mistakenly put in the to-do list by my colleague to the backlog list if it has more than 8 days before its due date.

This is the rule I wrote to move them from backlog to the to-do list if they hit 8 day mark to go there.

Screenshot 2023-08-17 at 10.22.48 AM.png

 

I wrote this and tested it and it did not work:

Screenshot 2023-08-17 at 10.29.49 AM.png

But I think what I want is to say > 9 days... and not have to write 9, 10, 11, 12, etc. versions of this rule.

Possible? Any suggestions?

 

1 answer

0 votes
Dreamsuite Mike
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 18, 2023

Hi @JERRY SAULMAN 

Welcome to the community.

Unless I am missing something here, can you use this command to prevent cards due in >8 days being moved to your to-do?

Screenshot 2023-08-18 111544.pngScreenshot 2023-08-18 111428.png

JERRY SAULMAN August 18, 2023

thanks I did not see that option!