You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Instead of manually dragging the timeline bar for each epic, I'm looking for a way for the child tickets to dictate the timeline based off dependencies and start/end date or target date. Is this possible?
Hello Justin,
Welcome to Atlassian Community!
The Epic date range is currently only manual. It will change if you drag its left and right to adjust or if you change the start and due date. The Epic won't adjust automatically if a child issue, for example, has the due date after the Epic's due date.
There are feature requests suggesting improvements for that:
Please, click on vote and also watch to receive updates about the features.