Portfolio 2.0 how to set portfolio start date?

This question is in reference to Atlassian Documentation: Configuring plan settings

My scrum teams have been using Portfolio 1.0 this year, and I want to recreate the plan in Portfolio 2.0.  However, I cannot find a way to set the portfolio start date in the new version, which is preventing me from accurately representing my teams' timeline for the year.  I understand that I could choose to only represent the work remaining to align the new schedule with the calculated schedule in Portfolio 1.0, but is there a way for me to backdate the new portfolio start, so that I can import my entire plan for the year?

1 answer

The "Earliest Start" field appears in under the "Scheduling" section of the detail view once you click on an issue—I assume this is what you are after?

Suggest an answer

Log in or Join to answer
Community showcase
Alexey Matveev
Published Saturday in Jira

How to run Jira in a docker container

Everything below is tested on Ubuntu 17.10. I prefer to use Jira in a docker container because: 1. I can install Jira with a couple of commands. 2. I can start and stop Jira just by starting and s...

47 views 1 3
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot