Is it possible to add issues to a rapid board for a sprint that has already started?

Mason Fitch August 28, 2012

I have setup a rapid board for Sprint 1 and while planning have started the sprint. I thought I'd be able to ad additional issues by dragging the tickets avove the Sprint Marker in the baclkog and updating the sprint. It's not showing the items above the Sprint marker on the Work view for Sprint 1.

1 answer

1 accepted

0 votes
Answer accepted
Renjith Pillai
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 28, 2012

Check the release notes of 5.9.1, this feature was added from that version.

https://confluence.atlassian.com/display/GH/GreenHopper+5.9.1+Release+Notes