Hi Guys,

In Greenhopper Rapid Board planning view, is there any configuration I could use to make story points of children tasks visible (see example)? Currently we have to edit the task to view the story points.

I have applied the following link and it works for Edit Issue screen:

https://confluence.atlassian.com/pages/viewpage.action?pageId=163939652

Would you have anything similar for planning view?

Is there any way we could have parent story point being populated automatically with the sum of all children story points?

Thanks,

Frederic

3 answers

1 accepted

1 vote
Answer accepted
frederic.maginot
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 19, 2013

Thanks for your answer. I will propose that to the team and see if it helps.

0 votes
Salem Korayem June 13, 2013

We've solved this: during the sprint, the team updates Story Points field on parent issue by asking "how much points are their remaining?" resulting in points reduction or increase. This makes the chart burn down though the issue is still in progress :)

0 votes
George Carvill
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 9, 2012

Actually, I think I found it:

switch from noreply to ${fullname}@mydomain.com

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events