Hi Guys,
In Greenhopper Rapid Board planning view, is there any configuration I could use to make story points of children tasks visible (see example)? Currently we have to edit the task to view the story points.
I have applied the following link and it works for Edit Issue screen:
https://confluence.atlassian.com/pages/viewpage.action?pageId=163939652
Would you have anything similar for planning view?
Is there any way we could have parent story point being populated automatically with the sum of all children story points?
Thanks,
Frederic
Thanks for your answer. I will propose that to the team and see if it helps.
We've solved this: during the sprint, the team updates Story Points field on parent issue by asking "how much points are their remaining?" resulting in points reduction or increase. This makes the chart burn down though the issue is still in progress :)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.