When viewing a burndown chart repot I really would like to be able to hide (or not include) non working days. They always cause burndown to -not burn down- over a weekend etc.
having this as a show/hide option would be great
Hi Axel, how's things? Sorry it's taken a while but I think you'll have to take it up with Atlassian. My original answer was for the normal burndown chart, not the rapid board charts (the question didn't say Rapid boards. although I should have guessed by the screenshot) .
The non-working days should work ok for classic burndown charts but the Rapid boards are still maturing as a product feature and the non-working days don't appear to work. There are a couple of jira issues you may want to watch & vote for.
https://jira.atlassian.com/browse/GHS-5117 - a very long comment trail, worth a read
https://jira.atlassian.com/browse/GHS-4631
It's up to Atlassian to take it from here, sorry.
You set your non-working days in theGeneral Configuartion section of greenhopper
https://confluence.atlassian.com/display/GH058/Specifying+your+General+Configuration#SpecifyingyourGeneralConfiguration-Non-WorkingDays
Thanks, but I already have the bulk setting at 5 day workweek. I also tried setting individual (static days) in Greenhopper general config without any effect in the burndown chart i.e. I set Sept 22/23 as non working but they still show up in the burndown as shown above.
just found out that the Greenhopper setting only apply to the classic as stated on the page "The configuration options below only apply to Classic Planning Board, Classic Task Board, Classic Chart Board and Classic Released Board." I am using the Rabit Board types, not the classic ones.
is there no reply ?
Same issue here. I'm trying remove the weekend from the burndown chart to get a more realistic prediction about the planned and done work.
Same issue here, I choose 5 working days, enter all holidays and they all show up in the burndown chart.....So you really get a false reading on the burndown chart.
Hi Mathew,
Hope the new borns will let you have some time really soon to get back and reply this one.....
Hi,
there is a story with the same content at Atlassian:
https://jira.atlassian.com/browse/GHS-5117
Also a similar question here with an answer from Atlassian
https://answers.atlassian.com/questions/63092/rapid-board-burndown-chart-work-days
thanks Axel, we took them to Australia to see the family, took a while to get back on our feet. babies with jet lag isn't much fun!
To those still interested: it's possible to modify the non-working days in the Burndown Chart, as of Greenhopper 6.1.1.