Connection of Jira Portfolio to Jira Agile

I noticed, that when updating the plan, the effort of the jira issue changed as well. I was not expecting that. How can I prevent my issues changing, when updating a plan?

1 answer

I believe you need to disable the estimate synchronisation setting in your plan configuration.

https://confluence.atlassian.com/jiraportfolioserver/synchronization-settings-715263142.html talks about how Update plan works, and it specifically mentions making sure that you have update estimates sync turned on. Assumption is that if you disable it, then you wont have this issue?

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published 50m ago in Jira Software

How large do you think Jira Software can grow?

Hi Atlassian Community! My name is Shana, and I’m on the Jira Software team. One of the many reasons this Community exists is to connect you to others on similar product journeys or with comparabl...

41 views 3 3
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you