Portfolio scenarios - changing sprint duration Edited

I currently have the default sprint duration in Portfolio set to two weeks.  I want to create a scenario where the sprint duration is three weeks instead of two (for all sprints, not just one).   Can I do that without changing the configuration for all scenarios in the plan?

 

To clarify, I see other questions where users want to have a custom sprint duration to accommodate holidays and what-not.   In other words, they run 2 weeks sprints, but a few times a year want to make it a 1 week or 3 week for the holidays.    I am not asking this question.

1 answer

0 votes

Hi @Vanessa Roberts,

 

If you change the sprint duration of a team it will then become part of the scenario as an uncommitted change, as long as this is not committed it won't impact other scenarios. You are not able to change the duration of an active started JIRA sprint.

Note: while from my personal experience I would generally advise to keep the number of uncommitted change to a minimum to ensure it doesn't grow out of control, it seems OK for your use case.

 

Cheers,

Thomas

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Nov 27, 2018 in Portfolio for Jira

Introducing a new planning experience in Portfolio for Jira (Server/DC)

In the past, Portfolio for Jira required a high degree of detail–foresight that was unrealistic for many businesses to   have–in   order to produce a reliable long-term roadmap. We're tur...

5,400 views 46 26
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you