How to set a task beginning and end date in BigPicture outside of the Gantt view?

I have a task that got a random start date somehow way in the future and it's a pain to move it manually in the gantt chart. Where else can I change the start/end date for this task?

(I'm using the default settings for Big Picture)

1 answer

if you've added the start and end date fields to the JIRA screen and issue type screen scheme then you can edit those fields right from the JIRA view/edit issue screen.

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Bridget Sauer
Published Thursday in Marketplace Apps

Calling all developers––You're invited to Atlas Camp 2018

 Atlas Camp   is our developer event which will take place in Barcelona, Spain  from the 6th -7th of   September . This is a great opportunity to meet other developers and get n...

352 views 0 6
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you