How to see sub-task hours in parent task Tempo report?

Is it possible to see sub-task hours in parent task Tempo report?

2 answers

Hi Vadim,

I set a copy here of the answer I sent you via the Issue you created in our Tempo Support system:


You can view the hours logged on subtasks in the Issue Timesheet for the Parent issue. To do so, you need to check the "Include sub-tasks" in the Timesheet Report view. Please take also a look at https://tempoplugin.jira.com/wiki/display/TEMPO077/Issue+Report+View for more information.

Regards,

Susanne

@Susanne Götz [T1 I do not see the "Include sub-tasks" option in Cloud.  Am I missing something?

Hi @Test Kimm,

It is available in the issue view, Tempo Time Tracking panel of parent tasks.include subtasks.pngRegards,

Susanne

@Susanne Götz [T1 I do have that selceted, however sub-tasks do not show in the reports.

Subtasks can be included in the Tempo Custom report.

Select Tempo, Reports, Custom report. Then select to filter by Issue. When filtering the Custom report by Issue, you have the option to include subtasks.

Regards,

Susanne

Like 1 person likes this

Hi @Susanne Barbara Götz

Do we have an option to use a filter there. ? Say I want to run results from multiple Stories with sub-tasks included. 

Selecting the issue one-by-one is really not a practical solution

Regards
Gikku

Like 1 person likes this

Hi Gikku,

This is not available in the current version of Tempo Timesheets, but I am forwarding this to the Product management team as a feature request.

Like 4 people like this

Hi @Susanne Barbara Götz, please let us know if a ticket has been created for this so others can vote on it. It would be valuable for my organization as well.  

Hi Ashley,

The feature request for this is in our backlog, but we do not longer have a public instance where users can vote or follow the issue. 

Regards,

Susanne 

Hey @Susanne Götz, it's really a bummer not to be able to see total efforts by epic because it does not include subtasks. Please prioritize this feature request

Like 1 person likes this

Agreed.  This would be a MOST helpful feature enhancement.  Any updates would be very much appreciated.  

What is the update on this? Is it built already? 

Like 1 person likes this

Hi. This would be awesome to have such a feature. For now, the grouping report is really poor for my needs.

Please advise - I need to know if it's possible to use Tempo to evenly distribute worklog of a parent issue onto all of its sub-tasks. If this is not implemented in Tempo yet, then please inform me if any funciton already exists which would automatically and evenly enable to scatter it on previously defined issues (e.g. if there are 8 issues then each one of it is to be saved per 1 hour time frame. Such action ought to take place after saving (anywhere) 8 hours long worklog of parent issue.

 

--

regards,

Dominik Maciejewski

Atlassian Support

Suggest an answer

Log in or Sign up to answer
This widget could not be displayed.
This widget could not be displayed.
Community showcase
Published Apr 03, 2019 in Marketplace Apps

How to estimate projects more accurately?

Gaining insight into your team’s effectiveness and choosing the right estimation technique.   Estimating projects is hard. It is because people have the tendency to underestimate the time thin...

288 views 2 9
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you