How do I create a Due Date post function for two days ahead?

Chad Milton
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 14, 2017

I would like to create a due date for issues once they reach a certain status in my workflow.

1 answer

0 votes
David Fischer
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 14, 2017

Hi Chad,

you did not mention if you were already using an add-on for workflow extensions. If not, you can certainly achieve your goal using JMWE for JIRA Server or JMWE for JIRA Cloud, depending on which JIRA platform you're using. You would be using the "Set Field Value" post-function (the exact syntax depends on whether you are on Server or Cloud).

David

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events