With the Gantt-Chart by Frank Polscheit it should work to generate planning dates / time estimation in an automatic way. But for me it doesn't work. Are we doing it wrong or is someone else also experiencing problems?
Hopefully, now it seems to be working as expected, i.e.:
Now the calculation and re-scheduling seems to be working. But of course, without values Gantt-Chart can not calculate the planned and end date, so original time estimation is needed.
The Default velocity used for calculating a minimum duration: 100.0%
So to be clear: Planned Start, Planned End and Original Estimate are all needed on the Epic, true?
But will the Epic bar be drawn if the attached story points don't have Planned Start and Planned End? but only storypoints and storypoints expended?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In the Gantt-Chart Global Configurations for the progress the JIRA time tracking can be used (as we do, hence we need the time estimation), or story points can be used.
Acc. to the description:
Issue Rescheduling
Re-scheduling as shifting planned start/end dates, keeping the duration in working days, for dependent issues as well as sub-issues will be performed, if:
Doing the first/initial work logging for an issue, the planning dates will be copied into their related baseline dates.
Issue dependency must be done by linking the related issues using the Gantt-Dependency type as configured on the Gantt-Admin-Panel (main JIRA-Administration screen). You have to configure the dependency types and create dependencies between issues using the JIRA standard link feature or interactive linking on a Gantt-Chart.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I'm having some issues getting anything meaningful to display, but it could be that I have incomplete data in our sandbox environment where we are testing this gadget.
The following seems to be required fields on Epics: Planned Start, Planned End, Original Estimate
The following seems to be required fields on Stories: Planned Start, Planned End, Story Points, Story Points Expended, Epic Link
Also... it seems that the Project must also have a non-zero velocity. True?
If all of this is true then we will not be able to use this gadget because we don't give stories Planned Starts or Planned End since that is not an Agile approach.
Ideally I would like for the Epics to have Planned Start, Planned End and show progress based on the sum of all storypoints and the sum of all Storypoints Expended. Is that possible?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.