Only issues added after the installation are seen in the gantt.
Note that existing issues don't have estimates. If I add or update estimates the issues show up.
Is there any way to get issues w/o estimates added prior to the plugin to be shown?
Yes I have re-indexed and restarted jira.
Hi Martin,
please switch to the related project administration, there select tab "Gantt-Chart". Enter a valid project start and end date, hit "change" to set that values and you will see an additional button "generate planning dates ..." on the bottom of the panel. Please enter a suitable default estimation in working days for those issues not having any original estimation been set. Finally, hit the button "generate planning dates ..." and all issues of that project without planning dates will be set. Depending on your amount of issues and infrastructure performance of your JIRA, it goes very fast or may be need longer. As result, you'll get a short note of the amount of updated issues.
If you have any further question, please do not hesitate to contact me at frank@polscheit.de
Regards,
Frank
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.